Working with the FB editor
3.8
Inserting complete interconnection from reference project
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
4. Press Insert button.
• The button can only be activated if the device in the reference project has the same de-
vice type and version as the project device.
• After the button has been pressed, the module assembly is compared. If there are rele-
vant deviations, the insertion is refused and a corresponding message is displayed.
• If an insertion is possible, you are asked if the FB interconnection is to be inserted.
5. Confirm the question if the copied FB interconnection is to be inserted with Yes.
• The FB interconnection is inserted and the Insert from referential project dialog box is
closed.
• After the insertion, an update of the project is required.