Step 3 step 4, Clip-loc – Metal Sales Clip-Loc Installation User Manual
Page 23
![background image](/manuals/567685/23/background.png)
CLIP-LOC
© Metal Sales Manufacturing Corporation/ Subject to change without notice/ Effective Date 2/03
812.246.1935 (Corporate Offi ce) • www.mtlsales.us.com
22
I
NSTALLATION
OF
P
ANEL
O
VER
D
ECKING
(
CONT
.)
SIDELAP SECTION
If roof slope is less than 3:12 apply a continuous bead of tube sealant across inside of clip.
1. If roof slope is less than 3:12, apply a continuous bead of tube sealant on inside of clip leg as shown.
Clip is not required at panel eave end.
2. Install clip over male leg of panel as shown. Make sure short leg of clip is over male leg of panel.
Clip spacing is determined from chart on (page 18) or from project design wind uplift requirements.
Design requirements take presidence. Bend down panel barb if necessary for clip to fit male rib.
3. Fasten clip to decking with number of recommended fasteners shown in chart on (page 18).
4. Refer to chart on (page 18) if installing over rigid insulation.
INSTALLING SECOND PANEL
1. If roof slope is less than 3:12,
1
/
4
" Bead Butyl Sidelap Sealant must be placed on top of male leg
in sidelap.
2. Place the second panel on top of previously installed panel so that panel ends are flush at eave.
3. Clip-Loc center rib must be snapped in place first followed by female rib. Start snapping panel at one
end and working to other.
4. Fasten at eave through panel, closure, and sealant into decking with (6) #9-12 x 1
1
/
2
" Woodscrew XL
fasteners per panel. Fasteners must penetrate closure and sealant.
5. Repeat steps 3 and 4 for remaining panels.
STEP
3
STEP
4
INSTALLING CLIP-LOC CLIP
1
/
4
" Bead Butyl Sidelap Sealant
Clip-Loc Panel
Clip-Loc Clip
Panel Barb
If roof slope is less than 3:12 apply a continuous row of
1
/
4
" Bead Butyl Sidelap Sealant on top of male leg.
Clip-Loc Fastening Pattern
#9-15 x 1
1
/
2
" Woodscrew XL
(6) per panel