Clip-loc – Metal Sales Clip-Loc Installation User Manual

Page 48

Advertising
background image

© Metal Sales Manufacturing Corporation/ Subject to change without notice/ Effective Date 2/03

812.246.1935 (Corporate Offi ce) • www.mtlsales.us.com

47

CLIP-LOC

E

AVE

(O

PTIONAL

F

LOATING

) O

VER

O

PEN

F

RAMING

All eave flashings must be installed prior to panel installation.
1. Position and install Cleat to wall with appropriate fastener, 1'-0" o.c. Make sure Cleat allows for proper Eave attachment.
2. Install Eave flashing by sliding open hem onto Cleat and resting the Eave flashing back against eave strut. To hold Eave

flashing in place fasten to substrate with #10-16 x 1" Pancake Head Driller at 1'-0" o.c.
3. Apply a row of Double Bead Tape Sealant across Eave flashing approximately 2” from face of Eave flashing.
4. Properly align and install Clip-Loc Inside Closures to accommodate Clip-Loc panel rib alignment. Closures must be lined up
with panel ribs for proper seal. Do not apply tape sealant on top of closure.
5. If two or more flashings are required, lap the flashing over the previously installed flashing by a minimum of 2" placing a bead
of tube sealant between the flashings and securing with pop rivets 2

1

/

2

" o.c.

#10-16 x 1" PHD (1'-0" o.c.)

Eave

Double Bead Tape Sealant

Cleat

Clip-Loc Inside Closure

Clip-Loc Panel

Clip-Loc panel must be anchored to open framing behind outside closure at all ridge, endwall, and peak

conditions to fi x the panel when using this fl oating eave detail.

Clip-Loc Clip

Clip-Loc Clip must be installed at eave for this fl oating eave detail.

3

1

/

2

" MIN.

0"-1

1

/

2

"

#10-16 x 1" PHD (1'-0" o.c.)

1:12 Slope
Minimum

INSTALLATION NOTES