Double Bead Tape Sealant
Clip-Loc Inside Valley Closure
Clip-Loc Panel
Clip-Loc Clip
Valley Plate
Valley
6" MIN.
All valley flashings must be installed prior to panel installation. If two or more valley flashings are required, valley must
be installed working from eave to peak.
1. Install Valley flashing against valley plate. To hold Valley flashing in place fasten to substrate with #10-16 x 1" Pancake Head
Driller at 4'-0" o.c.
2. Apply a row of Double Bead Tape Sealant across both sides of Valley flashing approximately 5" from center of valley.
3. Properly align and install Clip-Loc Inside Valley Closures to accommodate Clip-Loc panel rib alignment. Closures are
designated "Left" or "Right". Closures must be installed on both sides of valley flashing and lined up with panel ribs for proper
seal.
Do not apply tape sealant on top of closure.
4. If two or more flashings are required, lap the flashing over the previously installed flashing by a minimum of 2" placing a bead
of tube sealant between the flashings and securing with pop rivets 2
1
/
2
" o.c.
5. Once panels have been installed, (see pages 44-45), fasten through panel, closure, and sealant into valley plate with 6 fasteners
per panel. Fasteners must penetrate closure and sealant to eliminate closure movement.
#12-14 x 1
1
/
2
" SD XL (optional)
(6) per panel (see below)
CAUTION
Additional screws
may be required for
high snow loading
and steep slopes.
1:12 Slope
Minimum
INSTALLATION NOTES