Note: Insulation, eave, gutter, and valley flashings must first be installed before panel installation
can begin (see pages 46-49). Clip-Loc panels can be installed going from either left to right or right
to left looking from eave to peak.
1. If Floating Rake Zee is not used, go to STEP 2 else proceed.
2. Install Floating Rake Zee at all rake and rake parapet conditions. Square Floating Rake Zee to rake
condition. It is critical that Floating Rake Zee be square to building as this will control lignment
of panels.
3. Fasten to framing with #12-14 x 1

1

/

4

" Shoulder Self Driller screws at 1'-0" o.c. Do not over tighten

screws for it is imperative that the Clip-Loc roof system be allowed to fl oat.
4. If two or more Floating Rake Zees are required, butt ends. Do not overlap Floating Rake Zees.
5. After applying Floating Rake Zees, insulation can be installed. Roll out insulation eave to peak laying
side of insulation on Floating Rake Zees. Avoid sidelap of insulation directly beneath sidelap of panel
(insulation not shown for clarity).

I

NSTALLATION

OF

P

ANEL

O

VER

O

PEN

F

RAMING

INSTALLING FIRST PANEL

1. If Floating Rake Zee is not used, panel clips are required under fi rst panel, see STEP 3. Apply a row of
Double Bead Tape Sealant across Eave fl ashing approximately 2" from face of Eave fl ashing.
2. Properly align and install Clip-Loc Inside Closures to accommodate Clip-Loc panel rib alignment.
Closures must be lined up with panel ribs for proper seal. Do not apply tape sealant on top of closure.
3. If Floating Rake Zee is not used, square panel to rake condition. If Floating Rake Zee is used,
position the fi rst panel so female leg is on top of rake zee, panel ribs are aligned with inside closures,
and panel is at desired overhang. Additional overhang must be considered for wall panels.
4. Fasten through panel, closure, and sealant into framing with (6) #12-14 x 1

1

/

2

" Self Driller XL

fasteners per panel. See pattern below. Fasteners must penetrate closure and sealant.

STEP

2

STEP

1

Square Floating Rake Zee to Rake

Fasten Floating Rake Zee with
Shoulder Self Driller (1'-0" o.c.)

INSTALLING FLOATING RAKE ZEE (OPTIONAL)

Clip-Loc Panel

Square Panel to
Rake, align with
Panel Closure

Clip-Loc Inside Closure

Clip-Loc Fastening Pattern

#12-14 x 1

1

/

2

" SD XL

(6 per panel)