1. Once panels have been installed, slide Clip-Loc Turn-up Tool over end of panel and bend pan up until flush with top of panel rib.
Turn up all Clip-Loc pans (see page 19).
2. Apply a row of Double Bead Tape Sealant across panel, up and over all ribs approximately 2"-4" from panel end.
3. Install a Clip-Loc Outside Closure over tape sealant. Before continuing make sure closure placement will accommodate Peak
flashing. Set closure in tape sealant.
4. Once all closures have been installed, place a row of Double Bead Tape Sealant across the top of closures.
5. Position and install Cleat to wall with appropriate fastener, 1'-0" o.c. Make sure Cleat allows for proper Peak attachment.
6. Install Peak flashing by sliding open hem onto Cleat and resting the Peak flashing back over roof panel.
7. Fasten Peak flashing to Clip-Loc panel rib with a ¼-14 x

7

/

8

" Stitch XL 8"o.c. at every rib.

8. If two or more flashings are required, lap the flashing over the previously installed flashing by a minimum of 2" placing a bead
of tube sealant between the flashings and securing with pop rivets 2

1

/

2

" o.c.

Double Bead Tape Sealant

#

1

/

4

-14 x

7

/

8

" Stitch XL (8" o.c.)

Clip-Loc Panel

Clip-Loc Clip

Cleat

Clip-Loc Outside Closure

Peak

Double Bead Tape Sealant

#10-12 x 1" PHW (1'-0" o.c.)

1:12 Slope
Minimum

INSTALLATION NOTES

Clip-Loc panel must be anchored to solid deck behind outside closure at all ridge, hip, endwall, and peak