Leveling the floor-standing load frame, Leveling the floor-standing load frame 58, Equipment – MTS Criterion 40 - Manual User Manual

Page 58: Procedure

Advertising
background image

MTS Criterion

®

Series 40 Product Manual

58

Leveling the Floor-Standing Load Frame

Installation

Leveling the Floor-Standing Load Frame

Level the load frame immediately after you position it for installation. This
prevents the base from rocking and provides a level test surface for more accurate
test results.

Equipment

The following items are required:

Spirit or bubble level

8# hex key wrench for C44 model

10# hex key wrench for C45.105 and C45.504W model

24# open-end wrench for C45.305 model

28# open-end wrench for C45.605 model

Procedure

To level the frame base:

1. Place a spirit or bubble level on the center of the base beam.

2. Loosen the top nut on each leveling foot using the open-end wrench.

3. Using hex key wrench or open-end wrench, alternately adjust the height of

each leveling foot while you monitor the spirit or bubble level reading.

4. Rotate the spirit or bubble level 90° to verify that the load frame is level side

to side and front to back.

5. When the machine is level, tighten the top nut on each leveling foot using

the socket wrench.

Frame Base

Leveling Foot

Loosen the top nut.

Turn the top end of
the foot to adjust the
level.

Criterion_product manual.book Page 58 Monday, July 28, 2014 3:52 PM

Advertising