Figure 36 - Aligning and joining heat pipe main and Line Reactor (for 6600V only)

NOTE: There is no required order of operations for installing fans and hoods
and joining cabinets. Joining cabinets first allows roof-top access to the upper
bolts, but these are also accessible from the front if you choose to install the fans
first.

Figure 37 - Connecting the cabinets with M10 hardware (split drives only)

Cabinets Bolted Together at

Four Corners using M10 Bolts

81003-929

M10
Hardware

M10
Hardware for
Back Bracket