Rockwell Automation Publication 7000-IN007E-EN-P - June 2014

69

Pre-Commissioning Responsibilities

Chapter 4

Table 10 - Drive Line-up Status

All power connections are torqued as per Rockwell
Automation specifications. Refer to

Torque Requirements

for Threaded Fasteners on page 73

.

All customer power cabling has been meggered or hi-pot
tested before connecting to drive system.

Power wiring phase rotation has been verified per the
specific electrical diagrams supplied by Rockwell
Automation.

Initials

Date

Check

The medium voltage and low voltage power is available
for startup activities.

The motor is uncoupled from the driven load.

The load is available for full load testing.

Initials

Date

Check