2.4 SITE PREPARATION

Ensure that the site selected for installation of the RECON Water Heater includes:

 Access to AC Input Power at 120 VAC, Single-Phase, 60 Hz @ 20 Amps.
 Access to Natural Gas line at a minimum pressure of 4 inches W.C. with the unit

operating at maximum capacity

.

2.4.1 Installation Clearances

All RECON Models are packaged in enclosures having identical exterior dimensions. The unit
must be installed with the prescribed clearances for service as shown in Figure 2-1 (shown with
optional Sequencing Valve). The minimum clearance dimensions, required by AERCO, are
listed below. However, if Local Building Codes require additional clearances, these codes shall
supersede AERCO’s requirements. Minimum acceptable clearances required are as follows:

Sides: 24 inches
Front: 18

inches

Rear: 18

inches

Top: 13

inches

All gas piping, water piping and electrical conduit or cable must be arranged so that they do not
interfere with the removal of any panels, or inhibit service or maintenance of the unit.

Figure 2-1: RECON Water Heater Dimensions & Clearances

--WARNING! -

 Keep the unit area clear and free from all combustible materials

and flammable vapors or liquids

.

 While packaged in the shipping container, the unit must be

moved by pallet jack or forklift from the FRONT ONLY.

18”

18”

18”

96”

12.5”

25.5”

20.5”

43.5”

79.5”