Before You Begin

Page 3-2

MDE-5067 FedEx Islander PLUS FMS Installation Manual · March 2013

4

Grounding Method: Proper system grounding is an extremely important part of the system
installation. Grounds for all system devices must be wired to the breaker panel ground bus bar
which, in turn, must be grounded to a ground rod. A conduit ground does not provide a
sufficient ground. It is recommended that the neutral and ground bus bars be bonded together
unless prohibited by local codes.

Pre-installation Checklist

Following pre-installation checklist is designed to ensure proper installation:

DO NOT remove existing system before verifying that there are NO BARRIERS to
complete the Islander PLUS installation.
If issues are found, call Bob Griffith at 336-547-5654 IMMEDIATELY to discuss options.

WARNING

Description

Checkbox

Check that you have the correct Gasboy Supplied parts:

• PA093400810FX - Islander PLUS FedEx CUSTOM.
• Stage 2 FedEx Islander PLUS Install Guide.

Check the conduit layout, and ensure you have the proper supplies and
clearances to complete the installation.

Check all fueling positions for proper operation.

Check all hose reels for proper operation - All hose reels connected to the
existing system MUST be connected and controlled by the Gasboy Fleet
PLUS system.

Check the E-STOP system for proper operation.

Find the circuit controlling the current FMS. Verify this is a dedicated
circuit.

Trace and identify control wires in the existing system.

Know the function of the control wires.

Identify and label the handle switch (in-use), if available.

Identify and label the (line/load) or authorize wires.

Identify and label the pulser wires.

Identify and label the LAN/WAN connections.

Mark all control wires for use when installing the Islander PLUS system.