9.4 Replacing an Inverter

Requirements:

☐ The new inverter must be a micro inverter.
☐ The new inverter must be commissioned in your plant.
☐ The new inverter must be connected to the Sunny Multigate (see installation manual for the

Sunny Multigate).

☐ You must have the user role Installer or Plant administrator (see Section 10.1).

Procedure:

1. Select Plant Selection > "My micro inverter plant" in the page and drop-down menu if you

have several Sunny Portal plants.

2. Select Configuration > Device Overview in the page and drop-down menu.
3. Select the Overview of New Devices tab.
4. Select [Refresh devices]. Your plant is then searched for new devices.

☑ After around one minute, the new inverter is displayed.

5. In the row for the inverter to be replaced, select

.

☑ Sunny Portal establishes a connection to the new inverter via the Sunny Multigate.

Page 2 of the Configuration Assistant opens.

6. Follow the Configuration Assistant instructions.

Device replacement: Do not delete old device

If you delete the device that you wish to replace from Sunny Portal, all the device data is
irretrievably deleted.

• To retain the data of the old device in Sunny Portal, do not delete the device.