SMA SC 500CP XT Installation User Manual

Page 19

Advertising
background image

Property damage due to rupture of grounding conductors

The components are connected to the inverter via the grounding conductor. If the roof is not disassembled correctly,
the grounding conductors may be pulled out.

• Take care not to damage the grounding conductors during disassembly.

Procedure:

1. Disassemble the ventilation grid (see Section 7.2.3, page 42).

2. Pull the front edge of the roof forward and push upward.

3. Gently push the roof to the rear. In doing so, you push the roof

out of the guide rails.

4. Remove the grounding conductor from the inverter.

5. Remove the roof and set it down on a suitable surface.

6. Attach the hoist to all four lifting lugs.

7. Raise the crane hook slowly until the hoist is taut.

8. Ensure that the hoist is attached correctly.

9. Slightly raise the inverter.

4 Transport and Mounting

SMA Solar Technology AG

Operating Manual

19

SCCPXT-IA-E4-en-44