Heatilator • Constitution EPA Fireplace • 480-1091C

November 11, 2008

Figure 26.1 Ceiling/Attic Construction

Fire Risk

• Must maintain 2 in. (51 mm) air clearance

to insulation and other combustible

materials.

WARNING

Mark the Exit Point of the Roof

Locate the point where the chimney will exit the roof by

plumbing down to the center of the chimney. Drive a nail

up through the roof to mark the center. See Figure 26.1.

• Cut Out the Hole in the Roof

Measure to either side of the nail and mark the 14-1/2 in.

x 14-1/2 in. (368 mm x 368 mm) opening required. This

is measured on the horizontal; actual length may be larg-

er depending on the pitch of the roof. Cut out and frame

the opening. See

Chapter 25 of the Uniform Building

Code for roof framing details.

• Assemble the Chimney Sections Through the

Roof

Continue to add chimney sections through the roof open-

ing, maintaining at least a 2 in. (51 mm) air space to com-

bustible materials.

• Install the Roof Flashing

If a roof flashing is to be used, install the roof flashing

appropriate to the roof pitch and install a termination cap

and storm collar following the instructions shipped with

the cap.

For chase installations you can use a round termination

cap, a round telescoping termination cap or a square

termination cap (See pages 62-63). A chase installation

must use a chase top. Chase tops are available from your

dealer. See page 14 for building a chase.

• Install the Chimney Air Kit (required in Canada):

When installing the chimney air kit, follow the instructions

provided with this accessory. See page 22.

• Completion of the Enclosure

Complete the fireplace enclosure, allowing space for

outside air ducts. Electrical wiring should not come in

contact with the fireplace.

A minimum clearance of 1/2 in.

(13 mm) must be maintained between the fireplace

back and 1 in. (25 mm) minimum clearances to sides

and the enclosure.

NOTE: Wiring for fans must be done before framed

enclosure is completed. If using a Heat Zone kit, it also

must be installed before enclosure is complete.