Heatilator • Constitution EPA Fireplace • 480-1091C

November 11, 2008

This kit is tested and safe when installed in accordance with

this installation manual. It is your responsibility to read all

instructions before starting installation and to follow these

instructions carefully during installations.
Installation of this kit

MUST by performed by a qualified ser-

vice technician.
The Heat-Zone-Wood kit is carefully engineered and must

be installed only as specified. If you modify it or any of its

components you will void the warranty and you may possibly

cause a fire hazard. Installation must be done according to

applicable local, state, provincial and/or national codes.
Plan the location of the fireplace and warm air duct run(s).

D. Heat Zone Kit

Ceiling Register

Wall Register

Floor Register

Two Duct Kits

Ceiling Register

12 in. (305mm) minimum clearance

from register to ceiling

Possible Air Duct Runs / Locations

DUCT RUN REqUIREMENTS

MAXIMUM Duct Run = 40-ft. (12m)

MINIMUM Duct Run = 36 in. (914mm)

DUCTING MATERIAL

6 in. (152mm) B-Vent Only

DO NOT DUCT into existing furnace plenum

MINIMUM CLEARANCE TO COMBUSTIBLES

1 in. (25mm) from the B-Vent

1/2 in. (13mm) from top & bottom of outlet box

0 in. (0mm) from the sides of outlet box

12 in. (305mm) from wall register to ceiling*

*(See Figure 32.1).

CAUTION

ALL wiring should be done by a qualified electrician and

shall be in compliance with local codes and with the National

Electric Code NFPA/NEC No. 70-current (in the United

States), or with the current CSC22.1 Canadian Electric

Code (in Canada).

Figure 32.1 Minimum Clearances to Combustibles