2 daily and periodic inspections – Hitachi SJ700-2 Series User Manual

Page 48

Advertising
background image

5 - 2

5.2 Daily and Periodic Inspections

Inspection cycle

Periodic

Part to

inspect

Inspection item

Detail of inspection

Daily

Annual Biennial

Inspection method

Criterion

Test equipment

Environment

Check the ambient temperature,

humidity, and dust.

{

See Section 2.1, "Installation."

The ambient temperature must

be within -10

°C to +50°C without

congelation. The ambient

humidity must be 90% RH or less

without condensation.

Thermometer,

hygrometer,

recorder

Whole inverter

Check for abnormal vibrations and

noise.

{

Check visually and by listening.

There must be no abnormality

found.

General

Power supply

voltage

Check that the main circuit voltage

is normal.

{

Measure the voltage between the

main circuit terminals R, S, and T.

The measured voltage must be

within the allowable tolerance for

AC power voltage.

Tester, digital

multimeter

(1) Check the ground resistance

between the main circuit and

ground terminals with a megger.

{

Disconnect all input and output cables

from the inverter's main circuit terminal

block, detach the control circuit terminal

block from the inverter, and remove the

jumper for switching the inverter's

internal filter function. Subsequently,

measure the insulation resistance

between the ground terminal and the

jumper connecting all the following

terminals:

R, S, T, U, V, W, P, PD, N, RB, R0, and

T0

The measured ground resistance

must be 5M

Ω or more.

500 VDC class

megger

(2) Check screws and bolts for

loosening.

{

Retighten loose screws and bolts.

There must be no abnormality

found.

General check

(3) Check each part for any trace of

overheating.

{

Check visually.

There must be no abnormality

found.

(1) Check the conductors for

distortion.

{

Connecting

conductors and

cables

(2) Check the cable insulations for

damage.

{

Check visually

There must be no abnormality

found.

Terminal block

Check the terminal blocks for

damage.

{

Check visually

There must be no abnormality

found.

Inverter circuit

and converter

circuit (including

resistors)

Check the resistance between

terminals.

{

Remove all cables from the

inverter's main circuit terminal block.

Use a tester (in 1Ω range mode) to

measure the following:

- Resistance between terminals R,

S, and T and terminals P and N

- Resistance between terminals U,

V, and W and terminals P and N

See Section 6.5, "Method of

Checking the Inverter and

Converter Circuits." Standard

operating life of inverter circuit

until replacement: 106 cycles of

starting and stopping (*3)

Analog tester

(1) Check for liquid leak.

{

Smoothing

capacitor

(2) Check that the relief valve does

not protrude or swell.

{

Check visually.

There must be no abnormality

found.

Target operating life until

replacement: 10 years

(*1) (*3)

Capacitance

meter

(1) Check that no fluttering sound is

generated during the relay

operation.

{

Check by listening.

There must be no abnormality

found.

Main

circuit

Relay

(2) Check the contacts for damage.

{

Check visually.

There must be no abnormality

found.

(1) While performing a unit

operation of the inverter, check

the balance output voltage

among the individual phases.

{

Measure the voltage between the

cables connected to the main circuit

terminals U, V, and W.

The inter-phase voltage balance

must be as follows:

200 V class models: 4 V or less

400 V class models: 8 V or less

Control

and

protective

circuits

Operation

(2) Carry out a sequential

protection operation test, and

check the protective and display

circuits for any abnormality.

{

Short-circuit or open the protective

circuit

outputs

as

a

simulation.

An error must be detected

according to the sequence.

Digital

multimeter,

rectifier

instrument, and

voltmeter

(1) Check for abnormal vibrations

and noise

{

Turn the fan manually during the

inverter power-off status.

Cooling fan

(2) Check the joints for loosening.

{

Check visually.

The fan must rotate smoothly.

There must be no abnormality

found.

Standard operating life until

replacement: 10 years

(*2) (*3)

Cooling

system

Heat sink

Check for clogging.

{

Check

visually.

The heat sink must not be

clogged.

(1) Check that all LEDs light up

normally.

{

Check visually.

The LEDs must light up normally.

Monitor

(2) Clean the monitor.

{

Clean the monitor with a rag.

Display

Meter

Check that meter readings are

normal.

{

Check the meter readings on the

panel.

The readings must meet the

standard and control values.

Voltmeter and

ammeter

(1) Check for abnormal vibrations

and noise.

{

Check vibrations and noise visually,

by listening, and with physical

senses.

There must be no abnormality

found.

General

(2) Check for unusual smells.

{

Check for any unusual smells

caused by overheating or damage.

There must be no abnormality

found.

Motor

Insulation

resistance

Check the ground resistance

between all motor terminals and the

ground terminal with a megger.

{

Remove the cables from the

inverter's main circuit terminals U, V,

and W, connect the motor wires (for

three phases) with one another, and

measure the ground resistance

between the motor wires and the

ground terminal.

The measured ground resistance

must be 5M

Ω or more.

500 VDC class

megger

*1 The operating life of the smoothing capacitor is under the influence of the ambient temperature. Refer to Section 6.6, "Smoothing-Capacitor Life Curve," as a standard for the

operating life until replacement.

*2 The operating life of the cooling fan varies depending on environmental conditions, including the ambient temperature and dust. Check the status of the cooling-fan operation

during daily inspections.

*3 The standard operating life (number of years or operation cycles) and the data described in Section 6.6, "Smoothing-Capacitor Life Curve," are based on the expected design

life, but they do not indicate the guaranteed life of any parts.