105

in cloudy weather. This is normal, and does

not affect either the yield or the mode of

functioning of the solar inverter.

· Switching off

Disconnect the PV generator side first by

opening the PV generator switch, and

then the grid connection by isolating the

relevant mains fuse.

If your PV system does not have a PV

generator switch, you must disconnect

the grid connection first of all by isolating

the relevant mains fuse. When you do

this, a "grid error" will be entered in the

error memory of the solar inverter.

If the solar inverter is to be completely

disconnected (e.g. removal) from the PV

system, reconfigured or extended, the

cabinet cover must be removed. Pay heed

to all safety hints (Pages 90 and 91).

Open the main switch for the PV DC

voltage and the mains fuse as described

above. After a waiting period of at least

five minutes, the solar inverter will be

voltage-free.

Disconnection of the PV generator by

removing the TYCO SOLARLOK connectors

must never be performed under load. In

the event of non-compliance, the connec-

tors could be damaged by a strong electric

arc. In this case, the relevant connectors

must be replaced!

Remove the cabinet cover.

Check that the grid connection terminals

are voltage-free.

!