GE Industrial Solutions NEMA EVSE CHARGING STATION User Manual

Page 23

Advertising
background image

g

EV Charging Station

User Manual & Installation Instructions

GE EV Charging Station User Manual

23 of 86

The cables must extend 16” to 24” above the wall surface, or according to local codes.

Pull L1, L2 and ground wire into the enclosure assembly through the conduit hub. Similarly pull the
communication cable into the enclosure assembly through the second conduit.

IMPORTANT: EV Charging Station is rated for 208-240V power only. The EVSE must be connected to a
grounded, metal, permanent wiring system, or an equipment grounding conductor. This should be run
with circuit conductors and connected to the equipment grounding bar or lead on the EVSE.
Connections to the EVSE shall comply with all applicable electrical codes and ordinances.

Install the enclosure on the wall-mounting bracket. Insert the threaded portion of the conduit hub into
the hole of the enclosure. Fasten the conduit hub using the nut. Fasten the enclosure to the wall-
mounting bracket using the self-sealing washers and nuts from inside the enclosure as indicated in
Figure 22.

Torque all the nuts as per the torque specification in Table 1.

Figure 22: Wall-Mount Installation, Exploded View

Connect L1, L2 to the fuse block and ground wire to the ground bar shown in Figure 23.

WALL-MOUNT UNIT

¼-20 HEX NUT, ¼:

SEALING WASHER

SLEEVE STUD ANCHOR WITH

HEX NUT

WALL-MOUNT BRACKET

CONCRETE

ANCHOR

¾” CONDUIT HUB

(2) ¾” CONDUITS

Advertising