The cables must extend 16” to 24” above the pole surface, or according to local codes.

Pull L1, L2 and ground wire into the enclosure assembly through the conduit hub. Similarly pull the
communication cable into the enclosure assembly through the second conduit.

Install the Kiosk pole mounted unit, using the nuts and sealing washers as shown in Figure 28.

Torque all the nuts as per the torque specification in Table 1.

Figure 27 : Mounting bracket alighnment to the holes