Installer's Check List

Revision D

Introducing SlideSmart DC

Intro-5

I

NSTALLER

'

S

C

HECK

L

IST

The following list provides a high level overview of the tasks involved in installing the SlideSmart DC gate
operator. Take a moment to review the list and check off the items as you complete the install.

?

 Site Prep - concrete pad location/dimensions, distance from gate, chain height, and mounting

considerations: post or base extension, front or rear installation.

?

 Make sure gate installation complies with ASTM F2200 Standard Specification for Automated Vehicular

Gate Construction. And, install the supplied WARNING sign on both sides of the gate.

?

 Check for compliance with local codes, site conditions, and NEC standards.

?

 Install operator - (on concrete pad use four ½ - 13 x 3.5in long concrete wedge anchors.)

?

 Attach chain end bracket to gate at proper height.

?

 Attach chain to end brackets and feed under SlideSmart idlers and over chain sprocket.

?

 Tighten chain using tensioning bolts.

?

 Verify chain is level with idlers and parallel to operator and gate.

?

 Connect red wire to DC Power Switch.

?

 Turn DC Power ON.

?

 Complete Initial Setup Menu programming.

?

 Install the target magnet and make sure it is in line with and passes by the target sensor so it can be

recognized by the software programming.

?

 Connect AC Power.

?

 Connect all accessory devices.

?

 Set the Close Timer (through the User Menu).

?

 Set gate speed, if applicable (through Installer Menu). Refer to START (Smart Touch Analyze and Retrieve

Tool) in the Reference section.

?

 Set IES sensitivity, if needed (through Installer Menu).

?

 Check the Smart DC Controller software version. If needed, upload the latest version from

www.hysecurity.com. See Smart Touch Analyze and Retrieve Tool.

?

 Program changes through the Installer Menu depending on the accessory devices that you have installed.

?

 Give a copy of the operator instructions to the end user. Show the end user how to:

Remove the operator cover. Turn the power off and on to demonstrate learn limits after DC/AC cycles.

Turn the DC power switch off, which disengages the motor, and manually push the gate.

Test the red Emergency Stop Button located on the side of the control box. It can be accessed through a
hole in the cover. See illustration on page S-8.

?

 Take photographs of the completed installation site and save it in your business files.