Install the operator, by taking the following steps:
1. Place the operator on the pad to best suit the conduit as

shown in Figure 1-2. Use the operator as a template and
center it on the pad. The chain path must be parallel
with the gate.

2. Assess any limitations in the chain path such as gate

support posts. Adjust the operator’s location as required.
Mark the mounting locations based on gate, operator,
and chain requirements. Mark the drill point at the
center of the slot to allow for adjustments.
See Figure 1-4 and Figure 1-9.

3. Remove the operator from the concrete pad and drill the

holes for the concrete anchors. See

Tip.

4. Mount the operator with four ½ - 13 x 3½-inch

concrete anchors as shown in Figure 1-10.

5. For additional types of mounting options, refer to the

Appendix.

PUBLIC

PUBLIC

SECURE

SECURE

19" minimum

(48.3cm)

Conduit

cut out

21"

(53.3cm)

10

.

5"

(26.7cm)

1.6"

(4.1cm)

6.4"

(16.3cm)

10.38"

(26.4cm)

Chain
#40 Roller

slotted holes (4x) for
concrete anchors:

½ - 13 x 3½"

Concrete
pad

Gate

Chain to Gate
Ideal distance =
Minimum distance = 2½" (5cm)

3¾" (9.5cm)

Chain resides
inside gate
support posts

Gate support
posts

Gate support
posts

Left hand gate

SlideSmart

parallel with the
gate.

Mark the center of

Direction of
gate movement

(shown in full CLOSE
position)

when opening

Figure 1-10.

½ - 13 x 3½"

anchors (4x)

concrete

Concrete
pad

Grade
level

Concrete

base

Tip: To keep pinpoint accuracy while drilling
the mounting holes in the concrete, use a
3/16-inch bit to pilot the holes and then move
to a ½-inch drill bit.