Installation of the brocade dcx 8510-8, Time and items required – Brocade DCX 8510-8 Backbone Hardware Reference Manual User Manual

Page 23

Advertising
background image

Installation of the Brocade DCX 8510-8

Time and items required................................................................................................. 23

Preparing for the Brocade DCX 8510-8 installation........................................................ 24

Unpacking and installing the Brocade DCX 8510-8........................................................ 25

Items included with the Brocade DCX 8510-8................................................................ 26

Providing power to the Brocade DCX 8510-8 Backbone................................................ 27

Port numbering................................................................................................................27

Chassis slots................................................................................................................... 29

Cable management.........................................................................................................29

Time and items required

You can set up and install the Brocade DCX 8510-8 in the following ways:

• As a standalone unit on a flat surface.
• In a 19-inch Electronic Industries Association (EIA) cabinet, using the 14U Rack Mount Kit (provided).
• In a mid-mount telecommunications (Telco) rack, using the Mid-Mount Rack Kit available from your

Brocade DCX 8510-8 supplier.

This chapter describes how to set up the Brocade DCX 8510-8 as a standalone unit. For rack-mount
installation instructions, refer to the appropriate manual as described in the following table.

The following table describes the main installation and setup tasks, the estimated time required for
each, and the items required to complete the task based on a fully populated Brocade DCX 8510-8 (512
Fibre Channel ports using the FC16-64 port blades). Configurations with fewer ports require less time.
These time estimates assume a prepared installation site and appropriate power and network
connectivity.

Installation tasks, time, and items required

TABLE 2

Installation task

Time estimate

Items required

Site preparation and unpacking
Brocade DCX 8510-8

30 minutes

1/2-in. socket wrench (to remove pallet bolts).

#2 Phillips screwdriver(for cable management comb).

Pallet jack.

Hydraulic lift or assisted lift, able to raise to a minimum of
140 cm (55 in.), with a minimum capacity of 115 kg (254
lb). The Brocade DCX 8510-8 weighs 161.2 kg (355 lb)
with eight FC16-64 port blades installed (512 ports).

Installing rack mount kit

30 minutes

Refer to the 14U Rack Mount Kit Installation Procedure or
the Mid-Mount Rack Kit Installation Procedure.

Mounting and securing Brocade
DCX 8510-8 in rack

30 minutes