CAUTION
If you do not install a module or a power supply in a slot, you must keep the slot filler panel in
place. If you run the chassis with an uncovered slot, the system will overheat.

Slots are numbered from 1 through 12, from left to right when facing the port side of the Brocade DCX
8510-8. Port, application, and encryption blades can be installed in slots 1 through 4 and 9 through 12.

This section is applicable for all the following port, application, and encryption blades supported on the
DCX 8510 chassis:

Blade

DCX

DCX-4S

DCX 8510-4

DCX 8510-8

FC8-32E port blade

No

No

Supported

Supported

FC8-48E port blade

No

No

Supported

Supported

FC8-64 port blade

Supported

Supported

Supported

Supported

FC16-32 port blade

No

No

Supported

Supported

FC16-48 port blade

No

No

Supported

Supported

FC16-64 port blade

No

No

Supported

Supported

FCOE10-24 application
blade

Supported

Supported

No

Supported (only in
slot 1)

NOTE
Not supported in the same chassis with FC8-48E, FC8-64, FC16-48, FC16-64,
FS8-18, or FX8-24 blades.

FS8-18 encryption blade

Supported

Supported

Supported

Supported

FX8-24 application blade

Supported

Supported

Supported

Supported

NOTE
For complete list of limitations on the FCOE10-24 application blade, refer to the Fabric OS Release
Notes.

Time and items required

The replacement procedure for each blade takes less than 10 minutes. Removing and restoring
transceivers and cables may take longer depending on how many must be changed. The following
items are required for the blade and filler panel replacement:

• Electrostatic discharge (ESD) grounding strap
• Workstation computer
• Replacement blade or filler panel
• #2 Phillips screwdriver

Time and items required

Brocade DCX 8510-8 Backbone Hardware Reference Manual