2 preliminary steps, Preliminary steps – FUJITSU PRIMERGY MX130 S2 User Manual
Page 107
Advertising

MX130 S2
Upgrade and Maintenance Manual
107
HDDs and accessible drives
7.10.2 Preliminary steps
Before installing a 3.5-inch HDD, perform the following steps:
Ê
Follow all procedures described in section
"Opening the server" on page 48
Ê
Open the front cage as described in section
.
Ê
Locate the correct drive bay as described in section
.
7.10.3 Removing an additional 3.5-inch HDD out of the
5.25-inch ODD/HDD bracket
Figure 46: Cabling of HDD and ODD in 5.25-inch ODD/HDD bracket
Ê
Disconnect cables to the HDD.
1
Power cable connector P2 (see
"Power cable T26139-Y4012-V211"
)
2
SATA cable T26139-Y4028-V153
/
0
/
0
1
2
Advertising