Liebert 130 kVA User Manual

Page 36

Advertising
background image

User Manual

Hipulse - Single Phase ‘1+N’ UPS System

130 kVA - 110V

16




Parallel 1+N:

Use of differential circuit breakers on UPS unit inputs in a configuration with separate
inputs and one battery for each unit requires installation of a common device only on

the System Bypass Mains.


Use of differential circuit breakers on UPS unit inputs sharing a common battery

requires installation of device common to all the input lines. If inputs are configured

for separate mains, a common device will also be required for all System bypass
mains.


UPS Battery:

The UPS Battery is protected by means of a control circuit that operates the tripping

mechanism of an automatic circuit breaking device (having a variable trip setting).

The tripping mechanism using an undervoltage release coil that operates on a present
minimum voltage level.

The circuit breaker is essential for maintenance of the battery and is normally located
near to the battery installation. The characteristics and operation of the automatic

circuit breaker are given in Chapter 6.

Output of the System:
In the eventuality that an external distribution panel is used for load distribution, the

selection of protective device must proved discrimination with those that are use at
the input to the UPS module.

3.1.7

Cabling procedure

Once the equipment has been finally positioned and secured, connect the power

cables as described in the following procedure.


Study the connection diagram in the figures below.

1. Verify that the UPS equipment is totally isolated from its external power source and
all the UPS power isolators are open. Check that these supplies are electrically

isolated, and post any necessary warning signs to prevent their inadvertent operation.


2. Open the door(s) to the UPS cabinet and remove the lower protective cover to gain

access to the connections bars.


3. Connect the safety earth and any necessary bonding earth cables to the copper

earth bus busbar located on the floor of the equipment below the power connections.


Note: The earthing and neutral bonding arrangement must be in accordance with local and national
codes practice

Input Connections:

4. Connect the a.c. input supply cables to the input busbars (U1-V1-W1 terminals)
and the bypass a.c. supply cables to the bypass busbars (U3 - N3 terminals) and

tighten the connections.

ENSURE CORRECT PHASE ROTATION




Output System Connections:

5. Connect the system output cables between the output busbars (U2 - N2 terminals)
and the critical load and tighten the connections.





Advertising