Liebert 130 kVA User Manual

Page 37

Advertising
background image

User Manual

Hipulse - Single Phase ‘1+N’ UPS System

130 kVA - 110V

17

WARNING

If the load equipment will not be ready to accept power on the arrival
of the commissioning engineer then ensure that the system output
cables are safely isolated at their ends.

6. Connect the Battery cables between the UPS terminals (+/ -) and its associated
battery circuit breaker. Connect screened auxiliary cables from each battery circuit

breaker control board to the auxiliary terminal block (X3) of UPS of their metal frame of

the Battery breaker mounted in input transformer cubicle or Battery circuit breaker
box (if used).

As a safety precaution remove the battery fuse in the module until the arrival of

commissioning engineer.

OBSERVE THE BATTERY CABLE POLARITY

WARNING

Do not close the battery circuit breaker before the equipment has
been commissioned.



Input-module Parallel Connections:

7. 1+N Parallel UPS System: Inside the module there is an Parallel Connectors Board

mounted on the left hand side. Connect one end of the interconnecting ribbon cables

to interface connector (X1) of the first UPS module and the other end to connector (X2)
of the second module, and so to the next module until a closed loop is formed. (see

fig 8-2).


Auxiliary Connections:

8. Connect the auxiliary cables of any external interface/ signals to the respective

connections of the output auxiliary terminal block (X4).

9. Refit the lower protective cover.