Chapter 5 Checking the installation prerequisites

89

BCM200/400 4.0 Installation and Maintenance Guide

Chapter 5

Checking the installation prerequisites

Refer to the following sections for information on BCM system installation prerequisites:

•

“General requirements”

•

“Environmental requirements”

•

“Electrical requirements”

•

“Site telephony wiring requirements” on page 90

•

“System equipment, supplies, and tools” on page 91

General requirements

Before you install the BCM main unit or expansion unit, complete the following actions:

•

Determine the location for the BCM main unit (or expansion unit), telephones, and other
equipment based on spacing and electrical requirements.

•

Order the required trunks from the central office.

•

Ensure that you have all the equipment and supplies you need to install the system.

Environmental requirements

Ensure you meet the installation environmental requirements. The installation area must be:

•

a minimum of 4 m (13 ft.) from equipment such as photocopiers, electrical motors, and other
equipment that produces electromagnetic, radio frequency, and electrostatic interference

•

within 1.5 m (5 ft.) of a three-wire grounded electrical outlet

•

clean, free of traffic and excess dust, dry, and well ventilated

•

within the temperature ranges of 10°C and 40°C (50°F and 104°F)

•

between 20% and 80% non-condensing relative humidity

•

structurally strong enough and with enough space to support the BCM units

•

a minimum of 46 cm (18 in.) from the floor

Note: The installation area must be of sufficient height from the floor to prevent water
damage.