Inside ladder installation – Grain Systems Bin Accessories PNEG-1802 User Manual
Page 17
4. Inside Ladder Installation
PNEG-1802 Inside Ladder Instructions
17
Inside Ladder Standoff Bracket Requirements
Field drilling will be necessary for the standoff
brackets located in the middle of the sidewall
sheet. Drill two (2) 3/8" diameter holes directly
in line with the horizontal seam holes 18-3/4"
apart. Continue down the sidewall with
standoff brackets at every 16" spacing. Refer
to
.
Figure 4F
After completing the inside ladder, it will be
necessary to support the bottom of the ladder
to the concrete. Depending on the actual
installation, the amount of support may
vary. The supports are not supplied by the
manufacturer. If a bin sweep is to be used in
the grain bin, other considerations may be
necessary to assure there is no interference
with the equipment.
Figure 4G