Grain Systems Bin Accessories PNEG-1802 User Manual

Page 43

Advertising
background image

4. Inside Ladder Installation

PNEG-1802 Inside Ladder Instructions

43

Inside Starter Bracket and Ladder Placement

Refer to

Figure 4AN

and follow the correct dimensions as shown. The ladder starter brackets must be

located in line with the horizontal seam. Check the 4' ladder section to make sure the ladder rung dimples
are to the top. Attach to the starter brackets using the hole located 1" from top of the ladder. It will also be
necessary to field drill a 3/8" hole on the ladder section for the starter bracket. Field drill this hole 2" below
the pre-drilled hole that is 1" below the top of the ladder.

(See Figure 4AN.)

All standoff brackets must be

installed every 22" and attached to each 4' section required.

NOTE: Refer to

general detail information section on PNEG-1451 for additional details for standoff bracket

to ladder assembly.

Figure 4AN Inside Starter Bracket and Ladder Placement