Inside ladder installation (for stir-ator option) – Grain Systems Bin Accessories PNEG-1802 User Manual

Page 33

Advertising
background image

4. Inside Ladder Installation

PNEG-1802 Inside Ladder Instructions

33

Inside Ladder Installation (for Stir-Ator Option)

Inside Ladder Placement

The inside ladder package for Stir-Ator option includes the ladders and double the amount of short
standoff brackets. Begin by positioning the ladder directly under the manhole roof panel as shown in

Figure 4AB

and install the top standoff bracket as shown in

Figure 4AC on Page 34

. Then, place the

standoff brackets every 22" vertically on the sidewall sheets using the horizontal seam holes for every
other hole location. Use 5/16" x 3/4" bin bolts to attach the standoff brackets to the sidewall of the grain bin.

NOTE: Refer to general detail information section on PNEG-1420 for additional details for standoff bracket

to ladder assembly.

Figure 4AB

Advertising