4. Inside Ladder Installation

PNEG-1802 Inside Ladder Instructions

21

Inside Ladder Installation (for Stir-Ator Option)

Inside Ladder Placement

The inside ladder package for Stir-Ator option includes the ladders and double the amount of short
standoff brackets. Begin by positioning the ladder directly under the manhole roof panel as shown in

Figure 4M

and install the top standoff bracket as shown in

Figure 4N on Page 22

. Then, place the standoff

brackets every 16" vertically on the sidewall sheets using the horizontal seam holes for every other hole
location. Use 5/16" x 3/4" bin bolts to attach the standoff brackets to the sidewall of the grain bin.

NOTE: Refer to general detail information section on PNEG-1420 for additional details for standoff bracket

to ladder assembly.