Grain Systems Bin Accessories PNEG-1802 User Manual

Page 26

Advertising
background image

4. Inside Ladder Installation

26

PNEG-1802 Inside Ladder Instructions

Inside Ladder Standoffs Requirements

Field drilling will be necessary for the standoff
brackets located in the middle of the sidewall
sheet. Drill two (2) 3/8" diameter holes directly
in line with the horizontal seam holes 18-3/4"
apart. Continue down the sidewall with
standoff brackets at every 22" spacing.
Refer to

Figure 4S

.

Figure 4S

Inside Ladder Supports

After completing the inside ladder, it will be
necessary to support the bottom of the ladder
to the concrete. Depending on the actual
installation, the amount of support may
vary. The supports are not supplied by the
manufacturer. If a bin sweep is to be used in
the grain bin, other considerations may be
necessary to assure there is no interference
with the equipment.

(See Figure 4T.)

Figure 4T

Advertising