Chapter 4. Production Monitoring™ Administration

Managing the Asset Tree

4.6

Production Monitoring™ User Manual

IM8001

In order to connect a Welding Power Source to Production Monitoring™, you need to save an installation
key file for each power source using the Power Wave® Manager. Refer to the Power Wave® Manager User
Manual
for more details.

To add a Welding Power Source to Production Monitoring™:

Procedure

Details

1.

Save an installation key file with the Power

Wave® Manager.

Refer to the Power Wave® Manger User Manual
under Saving an Installation Key File.

2.

Click on the Group to which you want to add

the Welding Power Source.

For example, John at Advanced Manufacturing
wants to add a welder to Line 1.

3.

Click Add A New Asset at the top of the

Asset Tree.

A New Asset appears under the selected Group
and the Asset Properties section displays.

4.

Select

Welder from the Tree Node Type

drop-down.

The new Asset Configuration section appears
under the Asset Properties.