Managing the Asset Tree
Chapter 4. Production Monitoring™ Administration
IM8001
Production Monitoring™ User Manual
4.7
Procedure
Details
5.
Click on the Select button next to the
Configuration Import field and select the
installation key file that you created in step 1.
The installation key file ends in TOK
(e.g., 10.23.10.90.tok).
6.
Click Run Import.
The system places a check mark in the Enable Data
Collection on Welder checkbox for you and displays
a list of attributes for the Welding Power Source
next to Configuration.
You can use information from the Description to
name your power source in the Asset Tree if you
choose.
7.
Enter the name of the Welding Power Source
in the Name field under Asset Properties and
click Save Changes.
Congratulations! You have added a Welding
Power Source entry to the Asset Tree in
Production Monitoring™.
8.
Repeat steps 1 through 7 for each power
source you want to add to the Asset Tree.