7. Function Check - Check all machine controls for opera-

tion. (See Section 2.5 on page 2-8)

If optional equipment is installed on this machine refer to Section 3
for specific Pre-Start Inspection and Operation instructions.

2.4 DAILY WALK-AROUND INSPECTION

Begin the “Walk-Around Inspection” at item one (1) as noted on
the diagram (See Figure 2-1. on page 2-6). Continue around
machine checking each item in sequence for the conditions listed
in the following check list.

TO AVOID POSSIBLE INJURY, BE SURE MACHINE POWER IS “OFF” DUR-
ING “WALK-AROUND INSPECTION”.

DO NOT OPERATE MACHINE UNTIL ALL MALFUNCTIONS HAVE BEEN COR-
RECTED.

DO NOT OVERLOOK VISUAL INSPECTION OF THE BASE FRAME
UNDERSIDE. CHECK THIS AREA FOR OBJECTS OR DEBRIS WHICH
COULD CAUSE EXTENSIVE MACHINE DAMAGE.