4.2

95-8661

l-3

instAllAtion

wIRINg REQUIREmENTS
The simplest installation involves installing the sensor

into one of the UD10 openings and connecting the wiring

directly to the UD10. If the installation requires separation

of the C706x sensor and the UD10 Display, the sensor

can be connected to a STB sensor termination box, and

the C706x/STB combination wired to the UD10. In this

case, shielded cable is recommended to help protect

against interference caused be extraneous electrical

“noise.” In applications where the cable is installed in

conduit, the conduit should not be used for wiring to

other electrical equipment whenever possible. If other

equipment power wiring is run in the same conduit, the

cabling must be shielded. The maximum allowable

distance between the C706x sensor and UD10 Display

Unit is limited by the resistance of the cabling used.

INSTAllATION AND wIRINg pROCEDURE
1. Determine the best mounting locations for the

detectors.

2. Install the C706x sensor within the proper opening

in the UD10 or STB junction box. Mount the UD10/

C706x with the sensor oriented vertically and the

opening pointing down. The UD10 should be

electrically connected to earth ground.

noTe

The electrochemical sensor cell does not need
to be installed within the C706X housing while
installing and wiring the detector/junction box.
It is recommended to keep the sensor in the
manufacturer’s sealed shipping bag in a cool
storage environment until actual power-up and
calibration commissioning is performed. This
will ensure that the sensor will provide maximum
longevity.

3. Terminate all three C706x conductors at the proper

terminals. Refer to the appropriate illustration for

details.

4. Double check that all wiring is the proper size

and type and has been installed correctly. Check

operating voltage at the C706x sensor and the

UD10 Display Unit.

noTe

Do not apply power to the system with the junction
box cover removed unless the area has been de-
classified.

5. Proceed with startup and calibration.