Moving frames and integrated operations platform, Machine location and ventilation, Machine location and ventilation 48 – MTS Criterion 60 - Manual User Manual

Page 48

Advertising
background image

MTS Criterion™ Series 60 Product Manual

48

Moving Frames and Integrated Operations Platform

Installation

Moving Frames and Integrated Operations Platform

The packing materials may shift and loosen while moving the frame.

Moving the frame with loose packing materials may cause injury to
personnel and damage to the frame.

Remove the packing materials before moving the frame.

Note

Before the FSE arrival, it is the customer’s responsibility to arrange the
off-loading, unpacking, and moving of the testing system to the final site
location.

Note

If the testing system needs to be moved to another location after initial
installation, it is the customer’s responsibility to move and remount the
system.

Machine Location and Ventilation

To ensure proper ventilation, locate the load frame approximately 100 mm (4 in)
away from adjacent walls and equipment. Do not block the vent holes of the
machine.

For comfortable working conditions and proper equipment operation, heat
dissipation of the equipment must be considered in providing adequate heating or
air conditioning in the laboratory area. Heat dissipation can be approximated by
summing the heat losses going into the room (1 kVA is equivalent to 860 kcal/hr
[3,400 Btu/hr]) and the gains from other sources such as furnaces and personnel.

WARNING

Advertising