Moving the Load Unit to Its Final Location

To move the load frame:

1. Remove the cover board. If you ordered the safety enclosure, take it out and

store it in a suitable place (The MTS field service engineer will install it for
you). Take off the side boards. Remove the mounting bolts for the frame.
Attach customer-supplied hoist rings (M30 for C64.305 / C64.305E, M36
for C64.605 /C64.605E and C64.106 /C64.106E) to the frame.

2. Tie suitable slings to the hoist rings and lift the frame. Remove the pallet

under the frame.

Note

The clamps attached should not be removed from the frame.