Moving the Load Fame

Unloading

The customer will be responsible for all the unloading process if no Unloading
Service is purchased. In case of special agreement, an MTS field service engineer
can monitor the unloading, storage, and transportation process.

To unload the load frame:

1. Unload the load frame with reference to the lifting position marker

and the gravity center marker

.

2. Choose suitable slings according to the weight table.

3. Lift the crate with suitable slings as shown in the following figure.

4. Pay attention to the gravity center marker

on the crate to ensure

stable and balanced lifting.

Note

If the machine will not be installed right away, store it in a steady, dry and
corrosion free place. MTS is not responsible for damages caused by
improper storage.