Moving Frames and Integrated Operations Platform

MTS Criterion™ Series 60 Product Manual

Installation

57

Note

Verify the capacity of the overhead crane.Be absolutely careful not to
stop or transit within the field of action of the overhead crane.

4. Raise the hook slowly and move the platform to its final location.

5. Put the platform down and take off the chains. Adjust the levelness with the

feet under the platform.

6. Contact MTS Systems Corporation to arrange for installation services.

Note

If you can guarantee the safety, other tools like platform vehicle and
pallet jack can also be used to move the Integrated Operations Platform
to its final location.Other equipment, such as a platform vehicle and
pallet jack, can also be used to move the Integrated Operations Platform
to its final location. Safety guidelines for these methods are not provided
in this manual, but you will need to be aware of safety precautions if
using these methods.

Do not exceed 30

o

Hoist Rings M16