MTS Criterion™ Series 60 Product Manual
56
Moving Frames and Integrated Operations Platform
Installation
Moving the Integrated Operations Platform
Unloading
Choose suitable slings according to the Integrated Operations Platform and crate
weight. Wrap the sling through the crate pallet and raise it.
Moving the Integrated Operations Platform to Its Final Location
To move the Integrated Operations Platform:
1. Unpack the Integrated Operations Platform.
2. Choose suitable chains according to the Integrated Operations Platform
weight.
3. Attach the chains to the customer-supplied hoist rings (M16) on the
Integrated Operations Platform and hang the other end to the hook.