Configuring the system – Rockwell Automation 2364P Parallel DC Bus Supply Config. User Manual

Page 187

Advertising
background image

Publication 2364P-5.01 December 1999

Installation

15-15

Configuring the System

At this point, complete the installation for all the inverters as
indicated in the appropriate instruction manuals (but do not connect
any power to the inverters at this time).

Properly install any additional line reactors, fuses, MOVs, filters,
controls, or other components, as necessary.

Complete all internal wiring, grounding, and synchronous
communications wiring between drives, as necessary.

Connect all communication devices, motors, encoders,
tachometers, and any other components.

Complete the installation for the parallel configuration (do not
connect any power to the parallel configuration at this time).

Properly install any additional options that have not been
installed yet.

Configure all external communication, control, and monitoring
devices.

Ground any items that are not yet properly grounded.

For each RGU, verify that SW1 (on the RGU isolation board) is
set appropriately (typically (115V AC). Also, verify that J4 and
J5 on the RGU main control board are not jumpered.

Make sure that the circuit breaker settings are correct, and verify
that all circuit breaker switches in the entire system are in the off
position. Also make sure that the start switch is turned to off.

Note: More information about circuit breaker settings can be
found in 2364E-5.01, 2364F-5.01, or the circuit breaker
documentation.

1 15 V AC C ontrol Volta ges

SW 1

(Located on RGU Isolation Board)