Basic startup procedure, Starting the rgu – Rockwell Automation 2364P Parallel DC Bus Supply Config. User Manual

Page 193

Advertising
background image

Publication 2364P-5.01 December 1999

Setting Up the Parallel Configuration

16-3

Basic Startup Procedure

The basic startup procedure must be performed when starting a new
unit to configure the essential parameters for operating the unit.

The following items will be needed when starting up the RGU:

a multimeter (for reading voltage and resistance)

a HIM, GPT, or other programming device

Starting the RGU

1.

Verify that the start switch is turned to off and that the disconnect
lever is pushed to off.

2.

Verify that the disconnect levers for all inverters are pushed to
off.

3.

Visually inspect all wiring in the RGU (board connections, DC
bus terminals, customer connections, etc.).

4.

Push the RGU disconnect lever to on and turn the door-mounted
start switch to on. The RGU will power up and perform its
precharge routine.

!

ATTENTION: The basic startup must be performed
when starting a new unit, replacing the main control
board, or upgrading firmware. Improper parameter
settings may result in poor performance or equipment
damage.

ATTENTION: Do not enable the RGU until the basic
startup procedure has been completed.

Advertising