External Wiring

CHAPTER 9: EXTERNAL WIRING

9.1 INSTALLATION COMPLIANCE

All field wiring made during installation must comply with:

National Electrical Code NFPA 70 and any other national, state, provincial or local codes

or requirements.

In Canada, CSA C22.1 Canadian Electrical Code Part 1, and any other local codes.

WARNING!

ELECTRICAL SHOCK HAZARD.

Before making any electrical

connections to the unit, disconnect electrical power supply at the

service panel. Failure to comply can cause severe personal injury

or death.

NOTE

The line voltage terminals are located on the right set of terminals

23 through 40. The low voltage terminals are located on the left set

of terminals 1 through 22.

9.2 LINE VOLTAGE CONNECTIONS

To connect line voltage electrical power to the unit, perform the following.

Connecting Line Voltage to the Esteem Boiler

1. Connect a dedicated 120 VAC/15A service to the line voltage terminal strip on the wiring

panel below the Esteem boiler control module, as shown in Figure 8-3.

2. Route the incoming 120 VAC power wire through the provided openings in the bottom jacket

panel.

3. The unit is provided with a service switch located on the front panel, check local code

requirements for compliance.

NOTE

If local codes or conditions require an additional service switch, the

installer must install a fused disconnect for 15 amp (minimum)

service switch.