6  Electrical Connection

SMA Solar Technology AG

30

STP10-17TL-IA-en-32

Installation Manual

Cable Requirements

Connection of a Second Protective Conductor

In some installation countries, a second protective conductor is required in order to prevent a contact
current in the event of failure of the original protective conductor.
For installation countries falling within the scope of validity of the IEC standard 62109, the following
requirements are applicable:

• Installation of protective conductor at the AC terminal with a conductor cross-section of at least

10 mm² Cu.

or

• Installation of a second protective conductor at the earth terminal with the same cross-section as

the original protective conductor at the AC terminal (see Section 6.3.3 "Connecting the Second
Protective Conductor", page 34)
.

You must always observe the applicable regulations in the country of installation.

Position

Description

Value

A

Cable diameter

14 mm to 25 mm

B

Conductor
cross-section

1.5 mm² to 16 mm², with bootlace ferrule
maximum 10 mm²

C

Stripping length

approximately 12 mm

The PE wire must be 5 mm longer than the L and N wires.