7  Commissioning

SMA Solar Technology AG

56

STP10-17TL-IA-en-32

Installation Manual

7 Commissioning

7.1 Commissioning the Inverter

1. Check that the device is fixed securely to the wall (see Section 5 "Mounting", page 20).
2. Check that the country configuration is correct (see Section 6.5 "Setting the Country Standard

and Display Language", page 44).

3. Check that the AC grid cable is connected correctly (see Section 6.3 "Connecting the Electricity

Grid (AC)", page 29).

4. Check that the DC cables (PV strings) are connected correctly (see Section 6.4 "Connecting the

PV Array (DC)", page 35).

5. Close unused DC inputs with the appropriate DC connectors and sealing plugs

(see Section 6.4.4 "Connecting the PV Array (DC)", page 40).

6. Close all enclosure openings.
7. Dock the lower enclosure lid at an angle and

attach. The captive screws must protrude.

8. Pre-screw all six screws and then tighten them in the

sequence shown on the right (torque: 2.0 Nm).