2 ac connection procedure – SMA STP 10000TL-10 Installation User Manual

Page 32

Advertising
background image

6  Electrical Connection

SMA Solar Technology AG

32

STP10-17TL-IA-en-32

Installation Manual

6.3.2 AC Connection Procedure

1. Check the mains voltage and compare it with the permissible voltage range

(see Section 14 "Technical Data", page 92).

2. Disconnect the miniature circuit-breaker from all three phases and secure against reconnection.
3. Release all six captive screws of the lower

enclosure lid.

4. To remove the lower enclosure lid, lift it from the

bottom.

5. Check that the country setting of the inverter is correct using the supplementary sheet provided

with the default settings.
If the inverter is not set to the desired country standard, adjust the country standard by means
of the rotary switches (see Section 6.5.3 "Setting the Country Standard and Language Using
the Rotary Switch", page 51).

6. Remove the adhesive tape from the AC enclosure opening.

Advertising
This manual is related to the following products: