McDATA Sphereon 4300 Fabric Switch Installation and Service Manual

Installation Tasks

Desktop Installation

To install a switch on a desktop:

1. Remove the backing from the four adhesive rubber pads and

apply the pads to the underside of the switch. Ensure pads are
aligned with the scribed circles at each corner.

2. Position the switch on a table or desktop as directed by the

customer. Ensure:

— A grounded AC electrical outlet is available.

— Adequate ventilation is present, and areas with excessive heat,

dust, or moisture are avoided.

— All planning considerations are met. Refer to McDATA

Products in a SAN Environment - Planning Manual (620-000124)
for information.

3. Verify all field-replaceable units (FRUs) are installed as ordered.

4. Connect the AC power cord to the receptacle at the rear of the

chassis.

5. Connect the AC power cord to a facility power source that

provides single-phase, 100 to 240 volt alternating current (VAC)
current.

6. When the power cord is connected, the switch powers on and

performs power-on self-tests (POSTs). During POSTs:

a. The green power (PWR) LED on the front panel illuminates.

b. The amber system error (ERR) LED on the front panel blinks

momentarily while the switch is tested.

c. The green LED associated with the Ethernet port blinks

momentarily while the port is tested.

d. LEDs associated with Fibre Channel ports blink momentarily

while the ports are tested.

7. After successful POST completion, the PWR LED remains

illuminated and all other front panel LEDs extinguish.

8. If a POST error or other malfunction occurs, go to

MAP 0000: Start

MAP

to isolate the problem.

9. Go to

Task 3: Configure Product at the EFCM Basic Edition Interface

.