Filling the water system – ClimaCool UGW Manual User Manual

Page 16

Advertising
background image

www.climacoolcorp.com

14

Filling the Water System

It is imperative that the water systems are free from

debris prior to initial operation . See Water Treatment for a

comprehensive list of precautions on page 15 .

Filling, Purging and Leak Testing the System

After the water systems have been properly installed,

visually inspect all joints for tightness . If the chiller is to be

installed in an existing system, the cleanliness of the existing

system can be judged from the operating conditions of the

present machines . The cooling tower in particular, should

be inspected and cleaned, if required . It is good practice to

flush and, ideally, to acid wash the existing system before

connecting a new chiller .
The following method is recommended to fill and leak check

the water system for modules WITH Water Isolation Valves:
1. Close all water isolation valves inside each module

which isolate the individual heat exchangers .

2. Ensure that all drain valves are closed and that all water

main isolation valves are opened .

3. The system should be filled with clean water sent

through the strainers and the system checked for leaks .

4. Once the main water lines and the chiller headers are

filled with clean water, purge and repeat the filling

process at least three times .

5. All modules are equipped with ¾” fill and flush valves

with lines teed into the inlet and outlet connections into

and out of each heat exchanger . Ensure these ¾” valves

are CLOSED .

6. Open the water isolation valves inside each modular

chiller and repeat the filling process, this time also

checking for leaks inside each module .

7. Following the final filling and leak checking procedure,

air should be purged from the system .

The following system is recommended to fill and leak

check the water system for modules WITHOUT Water

Isolation Valves:
1. Ensure that all drain valves are closed .
2. All modules are equipped with ¾” fill and flush valves

with lines teed into the inlet and outlet connections

into and out of each heat exchanger . Ensure these ¾”

valves are CLOSED .

3. The system should be filled with clean water sent

through the strainers and the system checked for leaks .

4. Once the main water lines and the chiller headers are

filled with clean water, purge and repeat the filling

process at least three times .

5. Following the final filling and leak checking procedure,

air should be purged from the system .

Cleaning the System

The following method is recommended to properly clean

the water systems:
1. Before cleaning the system, install a temporary

bypass line between the main supply and return water

headers of both chilled and condenser water systems

when possible . Open the main header bypass lines to

divert the initial water flow around the module heat

exchangers until you are confident the circulating water

is mostly pure .

2. Provided main header bypass lines are installed, close all

water isolation valves inside all modular chillers equipped

with manual or automatic water isolation valves . If the

modules are NOT equipped with water isolation valves,

we recommend installing 3-way main header bypass

valves so the initial water flow bypasses all module

heat exchangers .

3. It is mandatory to run the pumps with the strainers in

place (see Starting the Pumps section below for proper

pump startup) . All external hydronic branches should be

open to all devices in the system .

4. Pressure drop across the strainer must be observed

and as pressure change reaches 50% of the initial read,

strainers must be isolated and cleaned .

5. Open all water isolation valves inside each module

equipped with manual or automatic water isolation

valves (see step 6 for modules NOT equipped with water

valves). If bypass lines are not installed (described in step

1) it is recommended to drain out the initial fill of water

to help flush out debris. Close off the main header bypass

lines referred to in step 1 and open the flow to the main

water headers . Repeat steps 3 and 4 until there is no

more debris being collected by the strainers .

6. If bypass lines are not installed (described in step 1) and

the modules are NOT equipped with water isolation

valves, it is recommended to drain out the initial fill of

water to help flush out debris. Remove and clean the

strainers before refilling and purging the system again.

Repeat steps 3 and 4 until there is no more debris being

collected by the strainers .

Starting the Pumps

Follow the manufacturer’s recommendations when starting

the pumps for the first time. The system should be checked

for leaks and air purged with the pumps in operation . The

pressure drop across the heat exchangers will give a good

indication of flow through the system (See Condenser

and Evaporator Water Pressure Drop Charts on page 17) .

This should be immediately checked against the expected

pressure drop for the flow rate required. If the pressure

drop begins to fall and the flow rate is falling, this could

indicate the need to clean the strainers.

Advertising