Startup – ClimaCool UGW Manual User Manual

Page 25

Advertising
background image

23

www.climacoolcorp.com

Startup

All startups must be performed by ClimaCool factory

trained personnel.
1 . Review all items are complete from the Pre-Startup

Check List .

2 . Cross reference model number with submittal sheet

to verify that the units are the correct model type and

voltage requirements .

3 . Verify the location and wiring connections of all main

header temperature sensors (should be a minimum of

36” from the bank). Confirm that all sensors are FULLY

INSERTED into their sensor wells and wired back to the

Master Control Panel .

4 . Verify the location and ports for all water differential

pressure sensors used for flow detection ((+) port piped

to the inlet headers and the (-) ports piped to the outlet

headers) .

• Verify the correct wiring using the +5VDC power

supply to the differential sensor inputs.

• Verify the correct output wiring from the differential

sensors back to the master controller universal input

(UI) channels 8 and 11. Confirm inputs 8 & 11 jumpers are

sset for ‘volts’ . Note: The differential sensor ports should

NOT be piped to a location which includes strainer

pressure drops .

5 . Verify that all header inlets (condenser and evaporator)

include strainer assemblies equipped with 60 mesh

screens .

6 . Inspect all refrigerant piping for oil leaks which may

have occurred during shipment which might indicate a

refrigerant leak . Check the high pressure cutout setting

of the pressure controls . The setting should be 385 psig

UGW models .

7 . Verify the location and settings of the phase

loss monitor . It should be in a location to sense the

voltage condition in the main, high voltage panel which

feeds high voltage to each module independently .

Verify the low voltage output wiring from the phase loss

monitor (terminals 4 and 5) back to the main CoolLogic

controller, input channel 12 .

8 . Determine if the chiller modules are equipped with

motorized water isolation valves . If so, verify the

settings of the motorized valves auxiliary switch dial

settings, to ensure they close near:

• 15% for source valve (condenser) and for load side

(evaporator or heat).

9 . Confirm that the main water pumps are driven by VFD’s,

and that all VFD’s are controlling the pump speeds to

produce a nominal differential pressure drop across

the chiller bank headers, measured precisely at the

differential pressure sensor locations in step 4 above.

Nominal differential pressure ranges are from 3 to

10 psid .

10 . Confirm the jumper locations for all master controller

and module controllers as shown on the wiring diagrams

provided on the inside electrical door panels .

• Set the rotary switches for the MAC Address of the

master controller to be “01 .”

• Set the rotary switches for the module controllers to

be “02” for module #1, “03” for module #2, and so on .

11 . Tighten every screw and lug connection inside the

CoolLogic master control panel and inside each module

control panel high voltage section . Check auxiliary

contacts on contactors ensure #1 auxiliary is wired on

the #1 contactor . Open up the compressor junction box

located on the front of each compressor and verify main

electrical terminal lug tightness and the low voltage

wires on protection module .

12 . Verify the communication cable wiring to ensure it is

18 AWG, simple two conductor shielded cable and that

the wiring is alone inside solid conduit between the

master control panel and the first module control panel.

Verify the cable’s outer jacket is not stripped more than

one inch . If so, the wires may have become untwisted,

causing signal reflections. Confirm the wires are

connected correctly to the terminal blocks at the

master and each module as follows:

Black wire to Net-

White wire to Net +

Shield wire to Shield

Verify that the shield part of the wires continues the

daisy chain connection through to the last module but,

that this shield is NOT connected to a terminal lug inside

any module .

13 . Power-up the master control panel and download the

appropriate clipping file into the master controller,

following the instructions, “Install Clippings to Master .”

14 . Power up each module control panel, turn OFF the two

toggle switches located on the inside bottom of the low

voltage side of the module electrical panel . Download

the appropriate clipping file into the module controllers,

following the instructions, “Install Clippings to Module .”

15 . Check for proper line or high voltage values at each

module input power block, and the 24 VAC low voltage

values for correctness (+/- 10% of nominal values).

16. On 208/230V units, confirm transformer(s) are properly

tapped for the measured incoming power supply .

17 . Use refrigerant gauge set suitable for R-134a, and

hook up to the suction and discharge ports of each

module’s compressor stages separately . Bump start

the compressor by using the manual run commands

from the Master Control Panel, (found in the FN 7, or

the service menu) . Bump the compressor only for 1-2

seconds to ensure the correct rotation of the scroll

compressors (indicated by a rising highside pressure

and a falling suction pressure) .

Advertising